Pre-Shipment Release Guide

What must be complete before any product leaves Nokturnal — across all release states.

Required for every shipment — regardless of release state

Release authorized

All operations, inspections and tests complete, documentation complete, nonconformances resolved. Only the Program Manager, QA or the Production Supervisor may release (SOP-850-001 §12). For customer deliverables the PM's authorization is written in the chatter of the delivery or manufacturing order (SOP-854-002 §6.7.2).

Inspections recorded

In-process inspections passed and signed on the manufacturing order in Odoo (Work Orders > QC, WI-860-001); incoming inspections recorded in Odoo QMS (WI-860-002). Final inspection and tests complete before release (SOP-850-001 §12).

NCRs resolved

All open nonconformances dispositioned in Odoo QMS (WI-870-001). Use-As-Is and Repair need MRB review and a customer concession through the Program Manager (SOP-870-001, WI-870-001). Note any waiver under Nonconformance/Waiver Information on F-860-001.

Export compliance

Hold the shipment if it leaves the U.S., is USML or non-EAR99, or the end use is uncertain. The Export Compliance and Contracts Manager documents the release; no controlled shipment departs before that, and red flags go to the Director of Production Operations (SOP-854-002 §6.9, P-825-001). Records in SharePoint GCCHigh.

F-860-001 signed

For customer-deliverable shipments: Material Delivery Report completed and signed by the Program Manager and attached to the Odoo delivery (SOP-854-002 §6.8.2). A packing list goes with every shipment.

In Odoo — from delivery order to shipment

  1. Open the delivery in Inventory > Operations > Transfers > Deliveries. Nothing is picked without a delivery order in Ready status (SOP-854-002 §6.7).
  2. The PM writes the release authorization in the delivery's chatter (customer deliverables).
  3. Check the inspections behind the shipment: the manufacturing order's inspections are passed and signed (WI-860-001), and any NCR is closed or dispositioned. Nokturnal Odoo has no shipping inspection set up, so Odoo does not hold the delivery for a quality check — the PM's authorization is the release control.
  4. Open the delivery's MDR tab. Prime Contract/PO No, Subcontract No., Project No and Invoice No are pre-filled from the sale order, contract and project (you can type over them). Choose the inspection and acceptance point, tick the included documentation, add waiver information and the CLIN/SLIN on each line, then Print > Material Delivery Report. It prints in the F-860-001 layout with the signer set in Inventory > Configuration > Settings (Material Delivery Report signer). The PM signs it.
  5. When the contract or PO calls for them, print the certificates from the delivery: Print > Certificate of Conformance or Print > Shipping Inspection Certificate. They are also listed under QMS > Reports > Certificates of Conformance (CoC) and QMS > Reports > Shipping Inspection Certificates (course Find shipping certificates). Check with Quality before sending one (see "Which Certificate of Conformance?" below).
  6. Validate the delivery when the carrier picks up or the shipment is dropped off, record the tracking number, attach the signed F-860-001 and the CoC before closing, and tell the PM (SOP-854-002 §6.10).

Training: Find shipping certificates · Receive, move and find stock (lesson "Ship a delivery order") · Raise and find an NCR. Help: Home > Help, sections "Receiving and shipping inspection" and "Shipping documents (MDR and invoice)".

Additional requirements by release state

P-830-002 §3. Pick the deliverable's release state.

Prototype Release

Phase: R&D · Gate that closes it: PDR · Odoo: ProtoREL

"Basic control so we can build it once and learn."

First builds. Speed and learning over repeatability. Known gaps are documented.

Before shipping, confirm all of the following

  • eBOM in Odoo PLM for the build being shipped, approved with the baseline design documentation by the Engineering Lead or Project Lead before the first build
  • At least one work center defined in Odoo (routing, tracking, and cost capture)
  • Parts sourced through vendors in the system
  • Build notes, learnings, known gaps and rework documented and retained as QMS records
  • Any handwritten or informal work instructions are legible, capture critical process parameters, and are retained
  • Changes affecting customer requirements, safety-critical items, interface control documents or regulatory requirements had documented review and approval
  • Customer is aware the deliverable is at ProtoRel

ProtoRel product may be delivered to a customer (P-830-002 §1); the intent is that it leaves Nokturnal under the configuration control its state requires. SOP-850-001 production controls do not apply to R&D builds, SBIR Phase I/II or technology demonstrations (SOP-850-001 §1); SOP-854-002 shipping steps still do.

Engineering Release

Phase: NPD · Gates: CDR, TRR · Odoo: EngREL

"This is the version we build, test, and improve against."

Repeatable builds. Configuration controlled. Design still open to refinement.

Before shipping, confirm all of the following

  • Normal BOM released (not provisional) in Odoo PLM; the part is released at EngREL
  • Drawings released, versioned and under configuration control
  • Work centers defined; basic work instructions documented — clear enough for a repeatable build
  • Test reports and relevant DVP&R (F-830-003) entries retained
  • Any controlled design changes since the last delivery have documented rationale

Changes affecting customer requirements, safety, or interfaces require a formal ECR/ECO — the development team manages other changes within project scope (P-830-002 §3.2).

Production Release

Phase: SUS · Gate: FDR · Odoo: ProdREL

"Everything is defined, controlled, and ready to scale."

Full production controls. Stable design. Built repeatedly without ambiguity.

Configuration & documentation

  • BOM fully defined and released in Odoo PLM (manufacturing BOM where applicable); all drawings fully released
  • Work instructions fully released (kept in Odoo PLM, SOP-850-001 §13); work centers finalized
  • Quality, test, calibration, supplier, and compliance records in place

Production records (SOP-850-001)

  • Manufacturing order operations complete; in-process inspection results recorded in Odoo Manufacturing or inspection records
  • Production traveler/router complete and filed in the OneDrive program folder
  • Serial or lot traceability recorded in Odoo Manufacturing where the contract or regulation requires it
  • Special process records on file (potting, conformal coat, etc. — if applicable)

Pre-shipment checks

  • FOD checks done per SOP-850-001 §8 and SOP-850-004
  • Certificate of Conformance, when the contract or customer PO requires one, signed by the Program Manager or Quality Technician (SOP-854-002 §6.8.3)
  • All contract-required documentation confirmed present (test reports, TDP, SW/FW docs, IUID, etc.)

Exception-based changes only at ProdRel. All changes need formal ECR/ECO and CCB approval before implementation (P-830-002 §3.3, SOP-831-001).

Confirm the checklist for the deliverable's release state before the PM authorizes release.

F-860-001 Material Delivery Report — documentation package

Tick each item included, as listed on the form. Package must be complete before the shipment leaves the building.

Included documentationWhen
Packing listEvery shipment (SOP-854-002 §6.8.1)
Certificate of ConformanceWhen the contract or PO requires it
Test reports / resultsIf required by contract
Technical Data PackageIf required
Software / firmware documentationIf applicable
User / operator manualsIf applicable
Training materialsIf applicable
Configuration management documentationIf required
Shipping declaration — hazardous materialsIf applicable
IUID registry documentationIf applicable

Also on the form: Nonconformance/Waiver Information and a signed certification statement. Export documents (EEI/ITN, Destination Control Statement, commercial invoice) are prepared by the Export Compliance and Contracts Manager for EAR/ITAR shipments (SOP-854-002 §6.8.4). Form: F-860-001 Material Delivery Report, or print it from the delivery in Odoo.

Which Certificate of Conformance? Two exist: the signed certification statement on F-860-001 (which also lists "Certificate of Conformance" as a separate included document), and the Certificate of Conformance Odoo prints from the delivery. SOP-854-002 §6.8.3 asks for an outbound CoC when the contract or PO requires one, signed by the Program Manager or Quality Technician and attached to the delivery, but does not name the form. Until Quality confirms which one is the official Nokturnal CoC, ask Quality.

Release control: Nokturnal Odoo has no shipping inspection policy or product shipping requirement set up, so validating a delivery is not blocked by a quality check. The Program Manager's written authorization in the delivery's chatter (SOP-854-002 §6.7.2) is the control. If you are unsure whether a shipment is ready, contact Quality before validating the delivery.

Reviewed November 2026 against SOP-854-002 v1.0, SOP-850-001 v1.1, P-830-002 v2.0, P-825-001 v1.0, SOP-870-001 v1.0, WI-870-001 v1.0, WI-860-001 v1.0 and F-860-001 v1.0. For internal use only · Owner: Quality