Guide: Product Release States
How to choose, record and move between ProtoRel, EngRel and ProdRel for hardware, software and combined deliverables. In Odoo the same levels are labelled ProtoREL, EngREL and ProdREL.
The 5 rules of thumb
How to apply P-830-002 to every contract type and funding source. Where this page and P-830-002 differ, P-830-002 governs.
Release state ≠ funding source
ProtoRel, EngRel, and ProdRel describe technical maturity and design control — not who paid for it. "Lifecycle state reflects what a deliverable is intended to be, not how the work is funded" (P-830-002 §2). An SBIR can produce ProdRel hardware. A cost-plus contract can produce ProtoRel deliverables.
Define start & target at kickoff
At project initiation the PM identifies the release state of each major deliverable in the Contract Classification (F-820-002; in Odoo, tab 4. Design Control: Planned Release States and Planned Release Transitions), including any planned state transitions (P-830-002 §4 and §4.1). Update it as the program evolves.
Three states, three mindsets
If your current activity doesn't fit the mindset of the state you've declared, your state assignment is probably wrong. Match the work to the mindset.
Iterations live inside a state
Run as many build-test-learn iterations as you need — they all happen within the current state. The state changes only when a gate review is completed with documented approval: typically PDR for ProtoRel → EngRel, and a mandatory CRB for EngRel → ProdRel (P-830-002 §5).
Track HW and SW separately
Different deliverables in one project may sit in different states (P-830-002 §2). Record the hardware and software states separately and plan both transitions. P-830-002 does not define a single state for a combined HW+SW product — see the Combined tab.
State selector
What type of deliverable?
Know your state
P-830-002 §3 and §6.
"Basic control so we can build it once and learn."
- eBOM required; may be incomplete. eBOM and baseline design documentation approved by the Engineering Lead or Project Lead before the first build
- At least one work center; vendors in the system
- No formal work instructions before the first build; handwritten notes OK afterwards if legible and kept as QMS records
- Iterative changes without formal ECR/ECO — except the mandatory change-control items (below)
- Gate that usually closes it: PDR
"This is the version we build, test, and improve against."
- Normal BOM released (not provisional)
- Initial drawing release; drawings versioned and under configuration control
- Work centers defined; basic work instructions documented
- Controlled changes with documented rationale; formal ECR/ECO for changes affecting customer requirements, safety, or interfaces
- Gates inside it: CDR (sets the design baseline) and TRR
"Everything is defined, controlled, and ready to scale."
- All drawings fully released; BOM fully defined and released (manufacturing BOM where applicable)
- All work centers finalized; work instructions fully released
- All supporting data in place: quality, test, calibration, supplier, compliance
- Changes exception-based, by ECR/ECO and CCB (SOP-831-001)
- Gate in it: FDR (production authorization)
Mandatory change control — every state. Regardless of release state, changes affecting customer-specified requirements, safety-critical features or critical items, interface control documents, or regulatory compliance requirements need documented review and approval before they are made (P-830-002 §3.1).
Customer deliveries. Each release state can be used to deliver product to a customer; what changes is how much configuration control the item carries (P-830-002 §1). CRB approval is mandatory before EngRel → ProdRel (P-830-002 §5.2). SOP-831-001 also requires that only Released parts are used in customer deliverables, and a part moves from Confirmed to Released at a CRB. Before anything ships, follow the Pre-Shipment Release Guide.
States are defined by decisions, not artifacts
Wrong: "We have one released drawing, so we're in EngRel."
Right: "We held the PDR and approved the move to EngRel, so now we release drawings and a Normal BOM." All transitions need a completed gate review and documented approval (P-830-002 Key Notes).
Common mistakes
| Mistake | Fix |
|---|---|
| "We have drawings, so we're EngRel." | Check whether the PDR was held and approved. The gate decision moves the state, not the artifact. |
| "IRAD doesn't need release states." | IRAD is a funding source. Release state follows technical maturity, risk and intended use (P-830-002 §2). Assign one at IRAD start (§4). |
| "We're in ProtoRel forever." | Plan the PDR when you need repeatability or a baseline. Work instructions must be in documented form before the EngRel transition (§3.1). |
| "One safety drawing makes us EngRel." | No. Safety-critical items, customer requirements, ICDs and regulatory items are under documented change control in every state (§3.1); controlling one item does not move the product to EngRel. |
| "We'll keep building from the Engineering BoM after EngREL." | Odoo refuses it: an Engineering BoM can be used on a manufacturing order only while the part is ProtoREL. EngRel needs a released Normal BOM (§3.2). |
Hardware-only release state
Work through these questions in order. Stop at the first question that points you to a release state.
| Question | Yes → action / state | No → continue |
|---|---|---|
| Is this feasibility, early exploration, or a first build where the primary goal is learning rather than repeatability? | ProtoRel eBOM required, approved by the Engineering Lead or Project Lead before first build authorization. At least one work center. Vendors in the system. No formal work instructions required before the first build. |
Design is beyond pure exploration. Continue to next question. |
| Is the engineering baseline stable enough for repeatable builds, and does the team need to build and test against a controlled baseline before committing to production? | EngRel Normal BOM released. Initial drawing release under configuration control. Work centers defined. Basic work instructions. Controlled changes with documented rationale; formal ECR/ECO for customer, safety, or interface changes. Entry typically at PDR completion (§5.1). |
Baseline not yet stable. Stay at ProtoRel and iterate. Plan the PDR when the §5.1 criteria are in reach. |
| Is the design verified and validated, and is the product intended for full-rate, repeatable production? | ProdRel Needs CDR and TRR complete, V&V complete per F-830-003 DVP&R, drawings and BOMs finalized and released, processes proven, quality and test procedures in place, supply chain qualified, compliance met, and CRB approval (§5.2). Changes afterwards by ECR/ECO and CCB only. |
Design not yet proven at production level. Remain at EngRel until the §5.2 criteria are met. |
| Regardless of state: is hardware being delivered to a customer? | Pre-shipment release Any release state may be delivered (§1). Use the Pre-Shipment Release Guide. SOP-831-001: only Released parts go into customer deliverables. |
Internal use. Keep build notes and learnings as QMS records. |
Documentation reminder. Record the hardware release state in the Contract Classification (F-820-002; in Odoo, tab 4. Design Control: Planned Release States and Planned Release Transitions) at project initiation and on the project's Current Project Release State (HW). Update both as the program evolves. Coordinate with Engineering, Operations, and Quality/Compliance (P-830-002 §4).
Software-only release state
Use this flow when the deliverable is software without associated hardware — e.g., standalone firmware, algorithm deliverables, or software updates to customer-owned hardware. P-830-002 states apply to software too ("whether software or hardware", §1); repository and versioning rules come from SOP-830-003.
| Question | Yes → action / state | No → continue |
|---|---|---|
| Is this exploratory code — algorithm prototyping, proof-of-concept, or feasibility testing — where the goal is to learn and iterate rapidly? | ProtoRel Iterative changes without formal ECR/ECO, except the mandatory change-control items (§3.1). Keep the code in a repository set up per SOP-830-003 and document learnings. |
Software is beyond pure exploration. Continue to next question. |
| Is the software being deployed to a controlled test environment, limited-quantity hardware, or a structured V&V program where repeatability and traceability matter? | EngRel Versioned builds under configuration control (SOP-830-003: semantic versioning, git tags aligned with binary releases). Verification planned in F-830-003 DVP&R. Changes with documented rationale; customer, safety, or interface changes by formal ECR/ECO. |
Not yet at structured test phase. Stay at ProtoRel. |
| Is the software being deployed to production hardware or systems where full-rate delivery, field maintenance, and long-term supportability are required? | ProdRel V&V complete per F-830-003 and CRB approval (§5.2). Formal, complete release: SOP-830-003 requires signed tags for releases and digital signing for production releases. Changes by ECR/ECO and CCB only. |
Software not production-ready. Remain at EngRel until V&V is complete and the §5.2 criteria are met. |
| Is software being delivered to a customer on any hardware or standalone medium? | Pre-shipment release Any release state may be delivered (§1). Physical shipments follow the Pre-Shipment Release Guide; electronic transfers of controlled software also need export review (P-825-001). |
Internal use. Keep the build traceable to its tag. |
Classified / air-gapped environments. For software deployed to classified or air-gapped environments, coordinate with the Software Engineering Manager. Offline (air-gapped) license activation follows P-850-001 Software License Management Policy.
Combined HW + SW
P-830-002 allows different deliverables in one project to carry different release states (§2, §4). It does not say which state a combined HW+SW product carries when the two differ.
Not yet decided — ask Quality. Earlier versions of this page said the less mature element governs the integrated product. Odoo does the opposite for engineering documents (it suggests the more advanced of the two). Until Quality/Compliance settles it, record the HW and SW states separately, plan both transitions, and agree the state you will claim for an integrated delivery with Quality before you ship.
What Odoo does with the two states
| Record | Where | Which state it uses |
|---|---|---|
| Project | Project form: Hardware Delivery / Software Delivery, Current Project Release State (HW) and (SW) | Holds both states separately. |
| Part | Part form: PLM Projects, Driving Project, Target Release Level | The linked project with the highest release level drives the part (for each project Odoo reads the HW state, or the SW state when no HW state is set). Linking a project to an assembly also links it to all its BoM children. |
| Engineering document | Engineering document form: Release State | Pulled from the project when you select it — the more advanced of the project's HW and SW states; can be changed while the document is in draft. |
| Program | Program form: Maturity Stage | One stage for the program, set by hand. ProdRel is refused until an approved CRB record exists. |
Quick scenarios
Every customer shipment, at any release state, goes through the Pre-Shipment Release Guide.
PM receives an SBIR Phase I contract to demonstrate a new tracking algorithm on a test unit. First hardware build, requirements still being refined.
ProtoRel Feasibility, requirements evolving, first build. eBOM approved before the build. If the contract delivers only reports or analysis, F-820-002 Section 3 routes it to Research Services (SOP-851-001) instead.
SBIR Phase II: the algorithm is proven, the team is building test articles to validate performance against a DVP&R. The customer wants limited units for evaluation.
EngRel Structured test against a controlled baseline (after the PDR). Normal BOM, released drawings, versioned software builds, F-830-003 DVP&R.
Contract for 50 production units. The design is fully validated, all V&V complete, and the customer requires an audit trail and long-term sustainment.
ProdRel Full-rate production after CDR, TRR and CRB approval. Final BOM, fully released drawings and work instructions, all supporting data. Production per SOP-850-001.
HW is at EngRel (test articles built, Normal BOM released). Engineering is rewriting the tracking SW from scratch for a new target class — the SW is exploratory.
HW EngRel SW ProtoRel Record the two states separately (Contract Classification and the project's HW and SW states). Plan the SW move to EngRel. Agree with Quality which state an integrated delivery carries.
Production HW (ProdRel) is being fielded with updated firmware that has not yet completed formal DVP&R. A customer delivery is needed urgently.
Firmware not ProdRel The firmware has not met the §5.2 criteria, so it can't be released as ProdRel. Changing a ProdRel product needs ECR/ECO and CCB approval (SOP-831-001). Bring it to Quality before shipping.
New IRAD: the team is breadboarding a novel sensor concept. No customer, no contract, no requirements baseline yet.
ProtoRel Pure exploration. The PM still assigns the state at IRAD start (§4). eBOM, documented learnings, and a plan for when the EngRel criteria will be assessed.
Gate review quick reference
SOP-830-001 §5 and P-830-002 §5. Phase gates are set by design complexity. Gates marked * are optional per SOP-830-001; the Design Plan says which gates apply. Review outcomes: Approved, Approved with Actions, or Not Approved (SOP-830-001 §5.2).
| Gate | Phase | Approval (SOP-830-001) | Release state (P-830-002) | Record |
|---|---|---|---|---|
| Kickoff | Concept / Planning | Project Lead | Project initiation: contract classification and initial release states (F-820-002). | Contract Classification in Odoo; engineering document with Gate Review = Kickoff if a record is kept. |
| PDR | Preliminary Design | Project Lead, Quality | ProtoRel → EngRel typically at PDR completion (§5.1), with first build done, learnings documented, baseline stable, basic work instructions written. | F-830-007 PDR Record; F-830-008 DR-PDR presentation template. Engineering document with Gate Review = PDR. |
| CDR* | Detailed Design | Project Lead, Quality, Customer (if required) | Held mid-EngRel; establishes the design baseline. Required before EngRel → ProdRel. | Engineering document with Gate Review = CDR. |
| TRR* | Build / Development | Project Lead | In EngRel. Required with CDR and CRB before EngRel → ProdRel; V&V recorded in F-830-003. | Engineering document with Gate Review = TRR. |
| Customer Demo* | Test / Validation | Project Lead, Customer | — | — |
| CRB | — | SOP-831-001: Engineering Manager (chair), Quality Manager, Manufacturing/Operations, Configuration Manager, Customer Representative when applicable. Unanimous consent. | Mandatory before EngRel → ProdRel (§5.2). Also the gate for a part from Confirmed to Released (SOP-831-001 §3.2.2). | Engineering document with Gate Review = CRB. Odoo will not set a program's Maturity Stage to ProdRel without an approved one. |
| FDR* | Delivery | Project Lead, Quality | In ProdRel: Final Design Review / production authorization (P-830-002 Figure 1). | Engineering document with Gate Review = FDR. |
Inside ProtoRel: informal iteration reviews vs. the formal PDR
Iteration reviews (informal)
Within ProtoRel you can build v1, v2, v3 and review each one however suits the project — team discussion, meeting notes, email approval. You may even call them "iteration PDR / CDR / TRR". They don't change the release state. In Odoo each iteration is a new part revision (Action > New Revision), and a ProtoREL part can be built from its Engineering BoM.
Formal PDR (the gate)
One formal PDR, recorded on F-830-007 and approved by the Project Lead and Quality, is what moves the product to EngRel. Plan it in the Design Plan: for example, "two or three iterations with informal reviews, then the formal PDR in month 4". After the PDR, build from a released Normal BOM.
Governing documents. P-830-002 Release State Control Policy · SOP-830-001 Design and Development Control · SOP-831-001 Configuration Management · F-731-001 CM Quick Reference · F-820-002 Contract Classification Form · F-830-003 DVP&R Workbook · F-830-007 PDR Record · F-830-008 DR-PDR Template Presentation · SOP-830-003 Software Development Standards · SOP-851-001 Research Services Procedure · P-850-001 Software License Management Policy
Planning gates in Odoo
Odoo labels the levels ProtoREL, EngREL and ProdREL (PLM) and ProtoRel (R&D), EngRel (NPD), ProdRel (SUS) (programs).
- Classify the contract. Programs & Projects > Program Control > Governance > Contract Classifications (or Start Classification on the project). Tab 4. Design Control holds Planned Release States, Planned Release Transitions and Design Release Rationale (P-830-002 §4). Then a PM clicks PM Approve and a PCM Manager clicks Quality Approve.
- Set the project's states. On the project, tick Hardware Delivery and/or Software Delivery and set Current Project Release State (HW) and (SW). Parts linked to the project follow it; linking a project to an assembly also links all its BoM children.
- Set the program's Maturity Stage. Programs & Projects > Programs > All Programs. The Documentation Baseline tab lists the Missing Required Deliverables for that stage. ProdRel is refused until an approved engineering document with Gate Review = CRB exists.
- Record each gate. Forms & Documents > Engineering Documents > All Engineering Docs: create the record, set Gate Review (Kickoff, PDR, CDR, TRR, CRB, FDR), attach the review record (F-830-007 for a PDR) and Submit for Approval.
- Release the parts. On the part, run the Pre-Release Analysis and click Release to ProtoREL / EngREL / ProdREL (PLM Release Users). The levels are kept in PLM/PDM > Configuration > Release States. Each iteration is a new revision (Action > New Revision). An Engineering BoM can be used on a manufacturing order only while the part is ProtoREL.
- Control changes. QMS > Change Management > Engineering Change Requests for ECRs and ECOs on released parts. An ECO does not change the part's revision or release level in PLM — do that by hand on the part.
Training
Check and release a part
Administer part numbering, pre-release rules and release levels
Build a ProtoREL prototype from an Engineering BoM
Control engineering documents
Request, approve and release an engineering change
Help in Odoo
Home > Help, sections "Release levels and projects", "Engineering documents (project records)", "Change management: ECR and ECO" and "Project governance: PMP, Contract Classification, access".
PM planning checklist
At project initiation (contract kickoff, IRAD start, or program approval), confirm all of the following (P-830-002 §4).
Release state decisions — Contract Classification (F-820-002)
- Classified the contract on F-820-002 (Odoo Contract Classification). If the deliverable is only reports or analysis, Section 3 routes it to Research Services (SOP-851-001).
- Identified each major deliverable as HW, SW, or combined, and assigned its lifecycle phase (R&D / NPD / SUS) and initial release state, considering intended use, technical maturity, risk, and delivery expectations.
- Documented any planned state transitions during the contract (P-830-002 §4.1).
- For combined HW+SW deliverables: recorded HW and SW states separately and agreed with Quality the state an integrated delivery will carry.
- Listed in the Design Plan which gate reviews apply (SOP-830-001 §5) and how many informal iterations are planned inside ProtoRel before the PDR.
- For ProtoRel: eBOM and baseline design documentation to be approved by the Engineering Lead or Project Lead before first build authorization.
- For EngRel → ProdRel: planned the CDR, TRR, V&V (F-830-003) and the CRB, and confirmed the CRB members (SOP-831-001).
- Coordinated with Engineering, Operations, and Quality. The classification is reviewed and approved by Quality/Compliance and Engineering Management (§4.1); the design approach by the Program Manager and Quality/Compliance (SOP-830-001 §4.1.5).
- Set the project HW/SW states and the program Maturity Stage in Odoo, and update them as the program evolves.
Questions? Contact your PM or the Quality/Compliance Manager. This page is guidance and a companion to P-830-002, SOP-830-001 and SOP-831-001. Where they differ, the controlled documents govern.
Guide: Product Release States
How to choose, record and move between ProtoRel, EngRel and ProdRel for hardware, software and combined deliverables. In Odoo the same levels are labelled ProtoREL, EngREL and ProdREL.
The 5 rules of thumb
How to apply P-830-002 to every contract type and funding source. Where this page and P-830-002 differ, P-830-002 governs.
Release state ≠ funding source
ProtoRel, EngRel, and ProdRel describe technical maturity and design control — not who paid for it. "Lifecycle state reflects what a deliverable is intended to be, not how the work is funded" (P-830-002 §2). An SBIR can produce ProdRel hardware. A cost-plus contract can produce ProtoRel deliverables.
Define start & target at kickoff
At project initiation the PM identifies the release state of each major deliverable in the Contract Classification (F-820-002; in Odoo, tab 4. Design Control: Planned Release States and Planned Release Transitions), including any planned state transitions (P-830-002 §4 and §4.1). Update it as the program evolves.
Three states, three mindsets
If your current activity doesn't fit the mindset of the state you've declared, your state assignment is probably wrong. Match the work to the mindset.
Iterations live inside a state
Run as many build-test-learn iterations as you need — they all happen within the current state. The state changes only when a gate review is completed with documented approval: typically PDR for ProtoRel → EngRel, and a mandatory CRB for EngRel → ProdRel (P-830-002 §5).
Track HW and SW separately
Different deliverables in one project may sit in different states (P-830-002 §2). Record the hardware and software states separately and plan both transitions. P-830-002 does not define a single state for a combined HW+SW product — see the Combined tab.
State selector
What type of deliverable?
Know your state
P-830-002 §3 and §6.
"Basic control so we can build it once and learn."
- eBOM required; may be incomplete. eBOM and baseline design documentation approved by the Engineering Lead or Project Lead before the first build
- At least one work center; vendors in the system
- No formal work instructions before the first build; handwritten notes OK afterwards if legible and kept as QMS records
- Iterative changes without formal ECR/ECO — except the mandatory change-control items (below)
- Gate that usually closes it: PDR
"This is the version we build, test, and improve against."
- Normal BOM released (not provisional)
- Initial drawing release; drawings versioned and under configuration control
- Work centers defined; basic work instructions documented
- Controlled changes with documented rationale; formal ECR/ECO for changes affecting customer requirements, safety, or interfaces
- Gates inside it: CDR (sets the design baseline) and TRR
"Everything is defined, controlled, and ready to scale."
- All drawings fully released; BOM fully defined and released (manufacturing BOM where applicable)
- All work centers finalized; work instructions fully released
- All supporting data in place: quality, test, calibration, supplier, compliance
- Changes exception-based, by ECR/ECO and CCB (SOP-831-001)
- Gate in it: FDR (production authorization)
Mandatory change control — every state. Regardless of release state, changes affecting customer-specified requirements, safety-critical features or critical items, interface control documents, or regulatory compliance requirements need documented review and approval before they are made (P-830-002 §3.1).
Customer deliveries. Each release state can be used to deliver product to a customer; what changes is how much configuration control the item carries (P-830-002 §1). CRB approval is mandatory before EngRel → ProdRel (P-830-002 §5.2). SOP-831-001 also requires that only Released parts are used in customer deliverables, and a part moves from Confirmed to Released at a CRB. Before anything ships, follow the Pre-Shipment Release Guide.
States are defined by decisions, not artifacts
Wrong: "We have one released drawing, so we're in EngRel."
Right: "We held the PDR and approved the move to EngRel, so now we release drawings and a Normal BOM." All transitions need a completed gate review and documented approval (P-830-002 Key Notes).
Common mistakes
| Mistake | Fix |
|---|---|
| "We have drawings, so we're EngRel." | Check whether the PDR was held and approved. The gate decision moves the state, not the artifact. |
| "IRAD doesn't need release states." | IRAD is a funding source. Release state follows technical maturity, risk and intended use (P-830-002 §2). Assign one at IRAD start (§4). |
| "We're in ProtoRel forever." | Plan the PDR when you need repeatability or a baseline. Work instructions must be in documented form before the EngRel transition (§3.1). |
| "One safety drawing makes us EngRel." | No. Safety-critical items, customer requirements, ICDs and regulatory items are under documented change control in every state (§3.1); controlling one item does not move the product to EngRel. |
| "We'll keep building from the Engineering BoM after EngREL." | Odoo refuses it: an Engineering BoM can be used on a manufacturing order only while the part is ProtoREL. EngRel needs a released Normal BOM (§3.2). |
Hardware-only release state
Work through these questions in order. Stop at the first question that points you to a release state.
| Question | Yes → action / state | No → continue |
|---|---|---|
| Is this feasibility, early exploration, or a first build where the primary goal is learning rather than repeatability? | ProtoRel eBOM required, approved by the Engineering Lead or Project Lead before first build authorization. At least one work center. Vendors in the system. No formal work instructions required before the first build. |
Design is beyond pure exploration. Continue to next question. |
| Is the engineering baseline stable enough for repeatable builds, and does the team need to build and test against a controlled baseline before committing to production? | EngRel Normal BOM released. Initial drawing release under configuration control. Work centers defined. Basic work instructions. Controlled changes with documented rationale; formal ECR/ECO for customer, safety, or interface changes. Entry typically at PDR completion (§5.1). |
Baseline not yet stable. Stay at ProtoRel and iterate. Plan the PDR when the §5.1 criteria are in reach. |
| Is the design verified and validated, and is the product intended for full-rate, repeatable production? | ProdRel Needs CDR and TRR complete, V&V complete per F-830-003 DVP&R, drawings and BOMs finalized and released, processes proven, quality and test procedures in place, supply chain qualified, compliance met, and CRB approval (§5.2). Changes afterwards by ECR/ECO and CCB only. |
Design not yet proven at production level. Remain at EngRel until the §5.2 criteria are met. |
| Regardless of state: is hardware being delivered to a customer? | Pre-shipment release Any release state may be delivered (§1). Use the Pre-Shipment Release Guide. SOP-831-001: only Released parts go into customer deliverables. |
Internal use. Keep build notes and learnings as QMS records. |
Documentation reminder. Record the hardware release state in the Contract Classification (F-820-002; in Odoo, tab 4. Design Control: Planned Release States and Planned Release Transitions) at project initiation and on the project's Current Project Release State (HW). Update both as the program evolves. Coordinate with Engineering, Operations, and Quality/Compliance (P-830-002 §4).
Software-only release state
Use this flow when the deliverable is software without associated hardware — e.g., standalone firmware, algorithm deliverables, or software updates to customer-owned hardware. P-830-002 states apply to software too ("whether software or hardware", §1); repository and versioning rules come from SOP-830-003.
| Question | Yes → action / state | No → continue |
|---|---|---|
| Is this exploratory code — algorithm prototyping, proof-of-concept, or feasibility testing — where the goal is to learn and iterate rapidly? | ProtoRel Iterative changes without formal ECR/ECO, except the mandatory change-control items (§3.1). Keep the code in a repository set up per SOP-830-003 and document learnings. |
Software is beyond pure exploration. Continue to next question. |
| Is the software being deployed to a controlled test environment, limited-quantity hardware, or a structured V&V program where repeatability and traceability matter? | EngRel Versioned builds under configuration control (SOP-830-003: semantic versioning, git tags aligned with binary releases). Verification planned in F-830-003 DVP&R. Changes with documented rationale; customer, safety, or interface changes by formal ECR/ECO. |
Not yet at structured test phase. Stay at ProtoRel. |
| Is the software being deployed to production hardware or systems where full-rate delivery, field maintenance, and long-term supportability are required? | ProdRel V&V complete per F-830-003 and CRB approval (§5.2). Formal, complete release: SOP-830-003 requires signed tags for releases and digital signing for production releases. Changes by ECR/ECO and CCB only. |
Software not production-ready. Remain at EngRel until V&V is complete and the §5.2 criteria are met. |
| Is software being delivered to a customer on any hardware or standalone medium? | Pre-shipment release Any release state may be delivered (§1). Physical shipments follow the Pre-Shipment Release Guide; electronic transfers of controlled software also need export review (P-825-001). |
Internal use. Keep the build traceable to its tag. |
Classified / air-gapped environments. For software deployed to classified or air-gapped environments, coordinate with the Software Engineering Manager. Offline (air-gapped) license activation follows P-850-001 Software License Management Policy.
Combined HW + SW
P-830-002 allows different deliverables in one project to carry different release states (§2, §4). It does not say which state a combined HW+SW product carries when the two differ.
Not yet decided — ask Quality. Earlier versions of this page said the less mature element governs the integrated product. Odoo does the opposite for engineering documents (it suggests the more advanced of the two). Until Quality/Compliance settles it, record the HW and SW states separately, plan both transitions, and agree the state you will claim for an integrated delivery with Quality before you ship.
What Odoo does with the two states
| Record | Where | Which state it uses |
|---|---|---|
| Project | Project form: Hardware Delivery / Software Delivery, Current Project Release State (HW) and (SW) | Holds both states separately. |
| Part | Part form: PLM Projects, Driving Project, Target Release Level | The linked project with the highest release level drives the part (for each project Odoo reads the HW state, or the SW state when no HW state is set). Linking a project to an assembly also links it to all its BoM children. |
| Engineering document | Engineering document form: Release State | Pulled from the project when you select it — the more advanced of the project's HW and SW states; can be changed while the document is in draft. |
| Program | Program form: Maturity Stage | One stage for the program, set by hand. ProdRel is refused until an approved CRB record exists. |
Quick scenarios
Every customer shipment, at any release state, goes through the Pre-Shipment Release Guide.
PM receives an SBIR Phase I contract to demonstrate a new tracking algorithm on a test unit. First hardware build, requirements still being refined.
ProtoRel Feasibility, requirements evolving, first build. eBOM approved before the build. If the contract delivers only reports or analysis, F-820-002 Section 3 routes it to Research Services (SOP-851-001) instead.
SBIR Phase II: the algorithm is proven, the team is building test articles to validate performance against a DVP&R. The customer wants limited units for evaluation.
EngRel Structured test against a controlled baseline (after the PDR). Normal BOM, released drawings, versioned software builds, F-830-003 DVP&R.
Contract for 50 production units. The design is fully validated, all V&V complete, and the customer requires an audit trail and long-term sustainment.
ProdRel Full-rate production after CDR, TRR and CRB approval. Final BOM, fully released drawings and work instructions, all supporting data. Production per SOP-850-001.
HW is at EngRel (test articles built, Normal BOM released). Engineering is rewriting the tracking SW from scratch for a new target class — the SW is exploratory.
HW EngRel SW ProtoRel Record the two states separately (Contract Classification and the project's HW and SW states). Plan the SW move to EngRel. Agree with Quality which state an integrated delivery carries.
Production HW (ProdRel) is being fielded with updated firmware that has not yet completed formal DVP&R. A customer delivery is needed urgently.
Firmware not ProdRel The firmware has not met the §5.2 criteria, so it can't be released as ProdRel. Changing a ProdRel product needs ECR/ECO and CCB approval (SOP-831-001). Bring it to Quality before shipping.
New IRAD: the team is breadboarding a novel sensor concept. No customer, no contract, no requirements baseline yet.
ProtoRel Pure exploration. The PM still assigns the state at IRAD start (§4). eBOM, documented learnings, and a plan for when the EngRel criteria will be assessed.
Gate review quick reference
SOP-830-001 §5 and P-830-002 §5. Phase gates are set by design complexity. Gates marked * are optional per SOP-830-001; the Design Plan says which gates apply. Review outcomes: Approved, Approved with Actions, or Not Approved (SOP-830-001 §5.2).
| Gate | Phase | Approval (SOP-830-001) | Release state (P-830-002) | Record |
|---|---|---|---|---|
| Kickoff | Concept / Planning | Project Lead | Project initiation: contract classification and initial release states (F-820-002). | Contract Classification in Odoo; engineering document with Gate Review = Kickoff if a record is kept. |
| PDR | Preliminary Design | Project Lead, Quality | ProtoRel → EngRel typically at PDR completion (§5.1), with first build done, learnings documented, baseline stable, basic work instructions written. | F-830-007 PDR Record; F-830-008 DR-PDR presentation template. Engineering document with Gate Review = PDR. |
| CDR* | Detailed Design | Project Lead, Quality, Customer (if required) | Held mid-EngRel; establishes the design baseline. Required before EngRel → ProdRel. | Engineering document with Gate Review = CDR. |
| TRR* | Build / Development | Project Lead | In EngRel. Required with CDR and CRB before EngRel → ProdRel; V&V recorded in F-830-003. | Engineering document with Gate Review = TRR. |
| Customer Demo* | Test / Validation | Project Lead, Customer | — | — |
| CRB | — | SOP-831-001: Engineering Manager (chair), Quality Manager, Manufacturing/Operations, Configuration Manager, Customer Representative when applicable. Unanimous consent. | Mandatory before EngRel → ProdRel (§5.2). Also the gate for a part from Confirmed to Released (SOP-831-001 §3.2.2). | Engineering document with Gate Review = CRB. Odoo will not set a program's Maturity Stage to ProdRel without an approved one. |
| FDR* | Delivery | Project Lead, Quality | In ProdRel: Final Design Review / production authorization (P-830-002 Figure 1). | Engineering document with Gate Review = FDR. |
Inside ProtoRel: informal iteration reviews vs. the formal PDR
Iteration reviews (informal)
Within ProtoRel you can build v1, v2, v3 and review each one however suits the project — team discussion, meeting notes, email approval. You may even call them "iteration PDR / CDR / TRR". They don't change the release state. In Odoo each iteration is a new part revision (Action > New Revision), and a ProtoREL part can be built from its Engineering BoM.
Formal PDR (the gate)
One formal PDR, recorded on F-830-007 and approved by the Project Lead and Quality, is what moves the product to EngRel. Plan it in the Design Plan: for example, "two or three iterations with informal reviews, then the formal PDR in month 4". After the PDR, build from a released Normal BOM.
Governing documents. P-830-002 Release State Control Policy · SOP-830-001 Design and Development Control · SOP-831-001 Configuration Management · F-731-001 CM Quick Reference · F-820-002 Contract Classification Form · F-830-003 DVP&R Workbook · F-830-007 PDR Record · F-830-008 DR-PDR Template Presentation · SOP-830-003 Software Development Standards · SOP-851-001 Research Services Procedure · P-850-001 Software License Management Policy
Planning gates in Odoo
Odoo labels the levels ProtoREL, EngREL and ProdREL (PLM) and ProtoRel (R&D), EngRel (NPD), ProdRel (SUS) (programs).
- Classify the contract. Programs & Projects > Program Control > Governance > Contract Classifications (or Start Classification on the project). Tab 4. Design Control holds Planned Release States, Planned Release Transitions and Design Release Rationale (P-830-002 §4). Then a PM clicks PM Approve and a PCM Manager clicks Quality Approve.
- Set the project's states. On the project, tick Hardware Delivery and/or Software Delivery and set Current Project Release State (HW) and (SW). Parts linked to the project follow it; linking a project to an assembly also links all its BoM children.
- Set the program's Maturity Stage. Programs & Projects > Programs > All Programs. The Documentation Baseline tab lists the Missing Required Deliverables for that stage. ProdRel is refused until an approved engineering document with Gate Review = CRB exists.
- Record each gate. Forms & Documents > Engineering Documents > All Engineering Docs: create the record, set Gate Review (Kickoff, PDR, CDR, TRR, CRB, FDR), attach the review record (F-830-007 for a PDR) and Submit for Approval.
- Release the parts. On the part, run the Pre-Release Analysis and click Release to ProtoREL / EngREL / ProdREL (PLM Release Users). The levels are kept in PLM/PDM > Configuration > Release States. Each iteration is a new revision (Action > New Revision). An Engineering BoM can be used on a manufacturing order only while the part is ProtoREL.
- Control changes. QMS > Change Management > Engineering Change Requests for ECRs and ECOs on released parts. An ECO does not change the part's revision or release level in PLM — do that by hand on the part.
Training
Check and release a part
Administer part numbering, pre-release rules and release levels
Build a ProtoREL prototype from an Engineering BoM
Control engineering documents
Request, approve and release an engineering change
Help in Odoo
Home > Help, sections "Release levels and projects", "Engineering documents (project records)", "Change management: ECR and ECO" and "Project governance: PMP, Contract Classification, access".
PM planning checklist
At project initiation (contract kickoff, IRAD start, or program approval), confirm all of the following (P-830-002 §4).
Release state decisions — Contract Classification (F-820-002)
- Classified the contract on F-820-002 (Odoo Contract Classification). If the deliverable is only reports or analysis, Section 3 routes it to Research Services (SOP-851-001).
- Identified each major deliverable as HW, SW, or combined, and assigned its lifecycle phase (R&D / NPD / SUS) and initial release state, considering intended use, technical maturity, risk, and delivery expectations.
- Documented any planned state transitions during the contract (P-830-002 §4.1).
- For combined HW+SW deliverables: recorded HW and SW states separately and agreed with Quality the state an integrated delivery will carry.
- Listed in the Design Plan which gate reviews apply (SOP-830-001 §5) and how many informal iterations are planned inside ProtoRel before the PDR.
- For ProtoRel: eBOM and baseline design documentation to be approved by the Engineering Lead or Project Lead before first build authorization.
- For EngRel → ProdRel: planned the CDR, TRR, V&V (F-830-003) and the CRB, and confirmed the CRB members (SOP-831-001).
- Coordinated with Engineering, Operations, and Quality. The classification is reviewed and approved by Quality/Compliance and Engineering Management (§4.1); the design approach by the Program Manager and Quality/Compliance (SOP-830-001 §4.1.5).
- Set the project HW/SW states and the program Maturity Stage in Odoo, and update them as the program evolves.
Questions? Contact your PM or the Quality/Compliance Manager. This page is guidance and a companion to P-830-002, SOP-830-001 and SOP-831-001. Where they differ, the controlled documents govern.